{"entry-date":"2025-03-20","start-date":"","end-date":"","entity":73000698,"name":"Phasing","dataset":"planning-condition","typology":"policy","reference":"U0110562","prefix":"planning-condition","organisation-entity":109,"geometry":"","point":"","quality":"authoritative","notes":"Unique Condition","reason":"To ensure that the local planning authority is satisfied with the phasing as proposed.","description":"Within 3 months from the date of this permission, a written programme specifying a phased order of work shall be submitted to the local planning authority for approval. The development shall be implemented in accordance with the approved programme."}