[{"fact":"8fac9b9c3987b99aea4d9154f078b0e304192346b31b0f848fac82248fd605fd","entity":73001319,"reference-entity":"","field":"description","value":"The development shall be carried out in accordance with the details referenced within the email from Peter Andrew to Roy Sykes (ref: Temporary Bridge, Evergreen, dated 9th August 2023) and the following mitigation measure shall be included: + The soffit level of the bridge shall be set no lower than 2.18 metres above Ordnance Datum, which provides a 1.00 metre freeboard above the design flood height. + The measure detailed above shall be retained and maintained thereafter throughout the lifetime of the development.","entity-name":"EA condition","entity-prefix":"planning-condition","entity-reference":"U0113338","earliest-entry-date":"2025-03-20","latest-entry-date":"2025-03-20","latest-resource":"6e210b1fa5551f87528b09d173fdd0a966e74dcacd9d417ebb30e847ddc5dc1c","resources":""}]