Piped discharge
Provenance
1 result
Fields:
description
| Fact | Field | Value | Latest Entry Date | |
|---|---|---|---|---|
| 7ec540439a12b0aa56fa6f184fceaad0c582632e3c28aa5d5e8f01ae634ee06d | description | There shall be no piped discharge of surface water from the development prior to the completion of surface water drainage works , details of which will have been submitted to and approved by the Local Planning Authority. If discharge to public sewer is proposed , the information shall include , but not be exclusive to:- a) evidence to demonstrate that surface water disposal via infiltration or watercourse are not reasonably practical; b) evidence of existing positive drainage to public sewer and the current points of connection; and c) the means of restricting the discharge to public sewer to the existing rate less a minimum 30% reduction, based on the existing peak discharge rate during a 1 in 1 year storm event, to allow for climate change. | 2025-03-20 |