Skip to main content

This is a new service - your feedback will help us to improve it.

Planning condition

FRA

Field Value Fact links
CURIE planning-condition:U0114007 no fact link
Prefix planning-condition Facts
Reference U0114007 Facts
Name FRA Facts
Quality We have no data no fact link
Dataset Planning condition no fact link
Organisation Doncaster Metropolitan Borough Council no fact link
Start date Facts
End date Facts
Entry date 2025-03-20 Facts
Typology policy no fact link
Notes Unique Condition Facts
Reason To ensure flood risk is minimised on the site without increasing risk elsewhere. Facts
Description The development shall be carried out in accordance with the submitted flood risk assessment (ref AEG02570_DN5_Bentley_07 / aegaea / 30/06/2023) and the following mitigation measures it details: o Finished floor levels shall be set no lower than 5.83 metres above Ordnance Datum (AOD) These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/ phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development. Facts

Contents

{
        "entry-date": "2025-03-20",
        "start-date": "",
        "end-date": "",
        "entity": 73001458,
        "name": "FRA",
        "dataset": "planning-condition",
        "typology": "policy",
        "reference": "U0114007",
        "prefix": "planning-condition",
        "organisation-entity": "109",
        "geometry": "",
        "point": "",
        "quality": "",
        "notes": "Unique Condition",
        "reason": "To ensure flood risk is minimised on the site without increasing risk elsewhere.",
        "description": "The development shall be carried out in accordance with the submitted flood risk assessment (ref AEG02570_DN5_Bentley_07 / aegaea / 30/06/2023) and the following mitigation measures it details: o Finished floor levels shall be set no lower than 5.83 metres above Ordnance Datum (AOD) These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/ phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development."
    }

© Crown copyright and database right 2026

Licensed under the Open Government Licence v.3.0.


Help improve this data

Give feedback on this dataset, or email your questions and corrections to digitalland@communities.gov.uk.